The Bradleys Road Wastewater Transfer Pump Station was required for the new 200mm rising main connecting Ohoka to the existing Rangiora Waste Water Treatment Plant.

Scope included:

  • Construction of new transfer building, inclusive of site preparatory works
  • Supply, installation of effluent storage tanks and interconnecting pipework
  • Supply, installation & commissioning of effluent pumps, motors, pipework and fittings
  • Supply and installation of electrical and pump station controls and communications
  • Supply and installation or all mechanical pipework, inclusive of underground drainage
  • Supply and installation of Perimeter fencing, Asphalt yard areas

The above project was initially above budget expectations, however through a collaborative approach savings of approximately $100,000 were provided to the client. In addition the project was completed 1 month ahead of the required due date for completion.

Share

Facebook Twitter Google + Linked In

Services Include: 

Project duration: 

August, 2012 to December, 2012

Client: 

Waimakariri District Council

Consultant: 

Spiire - Paul Reed

Contract value: 

$998,000

Want to know more?

If you’re looking for solutions for civil projects, or would like to know more about us and how we work, give Grant (027 247 1237) a call. Alternatively you can send us through an enquiry, by completing the form.

required
CAPTCHA
This question is for testing whether or not you are a human visitor and to prevent automated spam submissions.
l 03 381 7094