Case Studies

Project Case Studies

Kaiapoi Stormwater Basin Earthquake Repairs

February, 2013 - April, 2013

Ouruhia Radio Mast Foundation Remediation

October, 2012 - January, 2013

Following the September & February Canterbury Earthquakes, the 137m high radio mast foundations settled significantly and rotated. Ths was a consequence of lateral ground spreading and...

Bradleys Road Waste Water Pump Station

August, 2012 - December, 2012

The Bradleys Road Wastewater Transfer Pump Station was required for the new 200mm rising main connecting Ohoka to the existing Rangiora Waste Water Treatment Plant.

Scope included,

...

Huntsbury Reservoir No. 1 - Stage 2 Mechanical & Siteworks

June, 2012 - October, 2012

Working closely with Fulton Hogan, this project requires construction of 2 Insitu Concrete Valve Chambers complete with mechanical supply and installation including 450mm dia PE water supply main...

Southbook Stormwater Pond A Construction

January, 2012 - May, 2012

This project required a wide range of specialist skills including insitu concrete structures, drainage, continuous dewatering, earthworks, including impervious clay liner construction, trenchless...

Huntsbury Reservoir No. 1 Water Supply Pump Station

October, 2011 - December, 2011

This project is currently under construction, forming a critical part of the Christchurch Water Supply. As subcontractor to Fulton Hogan, Hunter Civil is responsible for the complete mechanical...

Ashburton District Bridge Replacements 2011

March, 2011 - May, 2011

This contract comprised demolition and replacement of 4 rural bridges within the Ashburton District. 3 of the bridges required new piling complete with either insitu or precast abutments and...

Southbrook Stormwater Pond C - Structures

January, 2011 - June, 2011

Subcontract to DELTA Utility Services to complete the following structures:

- 7m span portal bridge structure
- 5No. 4m x 1.5m reinforced concrete box culverts along Fernside Road...

DoC's Fox Glacier Splash Ford Replacement

October, 2010 - December, 2010

DoC's Splash Ford Replacement contract involved the following scope:

Site Clearance
1850m2 of cement stabilised and chipsealed bridge approaches
2800m3 of bulk fill for...

Mount Grey Foundation Strengthening

April, 2010

This contract was an upgrade of the foundation for the Mt Grey Communication Tower where the existing foundation required strengthening as additional services attached to the tower had...